2004/CZ/16/C/PE/002 - Příbram: WWTP Upgrading

Příbram: WWTP Upgrading - foto 1Příbram: WWTP Upgrading - foto 2Příbram: WWTP Upgrading - foto 3Příbram: WWTP Upgrading - foto 4Příbram: WWTP Upgrading - foto 5Příbram: WWTP Upgrading - foto 6Příbram: WWTP Upgrading - foto 7Příbram: WWTP Upgrading - foto 8
Příbram: WWTP Upgrading

The project included reconstructing and modernising the contemporary mechanical-biological WWTP at Příbram, which was unsatisfactory in terms of the requirements for municipal waste water treatment. The reconstructed WWTP has a capaTown of 62 500 PE. Within the project the coarse and mechanical preliminary treatment was reconstructed and the activation tanks and final sedimentation tanks were modified; tertiary treatment of waste water was also implemented. Sludge treatment was also reconstructed and the necessary common operation premises completed. A new system of measuring and regulating operations was built.

contractor: Project WWTP: Association SMEK (SEFIMOTA a.s. and Královopolská RIA, a.s. and MOTA - ENGIL ENGENHARIA E CONSTRUCAO, SA)
Project WWTP: SEFIMOTA a.s.
 
supervisor: D – PLUS PROJEKTOVÁ A INŽENÝRSKÁ a.s.

-

Total project cost:7 575 214 EUR
Total cost from the Financial Memorandum :7 348 400 EUR
Total eligible cost of the project:7 446 358 EUR
Total eligible cost from the Financial Memorandum :7 150 400 EUR
Rate of Cohesion Fund assistance:71%
Address of final beneficiary:The Town of Příbram
Tyršova 108
261 01 Příbram